Projects from 2009

Upcoming Projects

October 2009

Beth H. Acworth, GA ~ Eagle Pointe Church Chapter
    Projects Specs:
  • Work began on 10/24/09 but was not finished, 2nd day to be scheduled in Feb. 2010.
  • Work to be done:
      Outside
    1. Seal Windows
    2. Siding Repair
      Inside
    1. Check Ceiling in Bedroom
    2. Insulation
    3. Washing Machine Doesn't Drain
    4. Replace Ceiling Fan
    5. Painting
  • Financial Needs to Complete This Project: $300 currently $0 has been raised.
  • For Additional Information Contact:
ideas for fundraisers
 

December 2009

Allen C. Marietta, GA ~ Eagle Pointe Church Chapter
    Projects Specs:
  • Work to begin and finish on 12/5/09.
  • Work Completed:
    1. Repair Fence
    2. Remove Deck and fill sink holes
    3. Repair Eaves
    4. Replace Siding
    5. Landscaping
  • Finanacial Needs to Complete This Project: $900 currently $0 has been raised.
  • For Additional Information Contact:
    • Project Manager (PM): Kim Robinson
    • Assistant PM:
    • Volunteer Manager: Tim Roman
ideas for fundraisers
 
 

Past Projects

September 2009

Gary E. Acworth, GA ~ Eagle Pointe Church Chapter
    Projects Specs:
  • Work began on 9/19/09 and finished on 9/26/09.
  • Projects Completed:
    1. Painting Interior
    2. Floor Repair
  • Project Leaders:
    • Project Manager (PM): Scott Lohr
    • Assistant PM: Tim Roman
 

July 2009

Shelly R. Marietta, GA ~ Eagle Pointe Church Chapter
    Projects Specs:
  • Work began and was finished on 7/11/09.
  • Projects Completed:
    1. Landscaping
    2. Soffit Repair
    3. Interior & Exterior Replace Rotting Wood
    4. Plumbing
    5. Painting Interior
    6. Minor Cabinetry Work
    7. Mold Removal from Ceiling & Wall
  • Project Leaders:
    • Project Manager (PM): Steve Daniele
    • Assistant PM: Brad Vawter
    • Volunteer Manager: Rusty Draper
  • Special Notes:
    • Lunch has been donated by Chic-fil-A
 